Define the sample state
T1 describes an early tooling sample stage, but its exact commercial meaning should be agreed. Record the die revision, cavity, material, process condition and any machining or finishing already completed. A raw casting cannot demonstrate a final coated fit or the behavior of a complete assembly.
Separate disposition from production release
Use a dimension report and an issue list that assigns each open item an owner and next action. Distinguish tool correction, drawing clarification and accepted deviation. Approving selected dimensions does not release every requirement. State the evidence needed for the next trial and who authorizes repeat production.
Review checklist
| Review item | Define before release | Evidence to retain |
|---|---|---|
| Identity | Tool revision, cavity and material | Sample labels |
| Requirement coverage | Raw, machined, coated or assembled | Inspection scope |
| Open issues | Disposition, owner and next evidence | Trial action list |
Worked review example
If T1 proves the mounting pattern but the coating trial is pending, record a partial technical disposition. Do not describe the entire part as production-approved.
Apply the review to your drawing
Identify the affected features on the current drawing and attach the material, finish and operating requirements that control them. Agree the proposed route and acceptance evidence before releasing a change. Send the controlled files for a project review.